Those of you who have been rolling up your sleeves are to be congratulated for the excellent job you’ve done thus far. Thanks for getting involved. God has blessed Encounter Church with talented, hardworking and generous individuals.
Earlier this morning the electrician and his crew arrived to the job site and began the process of wiring the space. Their work should take about 3 days. Once the electrician has completed his work, the local building inspector will be coming to inspect the work that has been done. Upon passing the inspection, we’ll then begin the drywall process.
On Friday, November 5, and Saturday, November 6, two work teams from Ohio and Indiana will be coming to hang and finish drywall. Even though there will be work teams from out of state, we still need a lot of volunteers from Encounter to take part in these two long days of drywall work. Make plans to be involved.
We will begin priming and painting walls the week of November 8. On November 13, we’re planning for a big day of painting.
As soon as the painting is complete, the process of staging and setting up the building will take place.
The plan is to have our first Worship Gathering in the new location on Sunday, November 28. Our Grand Opening Worship Gathering will take place on Sunday, December 5.
Take time to pray for the following requests…
- Pray for the continued safety of the volunteers and workers.
- Pray for the upcoming inspections. Pray that we would pass the inspection without any delay.
- Pray for unity during this time of transition.
- Pray for greater opportunities to engage the culture with God’s Love and Truth through this new location.
- Pray that God would not allow us to lose our focus of reaching people.